The locker rooms and bathrooms have all been framed in, doors and windows are installed, and the wall between the lounge and the ice shed has gone up. You can really imagine yourself standing there watching games through the big windows now!
Then there has been a lot of little stuff, like additional bracing between the supports, adding overhangs, and installing a sheet of metal around the bottom of the building where the exterior walls will connect. Latest pictures are below...
Overhangs will help provide a bit of shade on the side of the building.
Lots of framing....looking more and more like an actual building.
We hope you'll be coming through that door soon!
Women's locker room and bathroom.
All the interior walls framed in. Locker rooms, bathrooms, storage area.
The wall separating the lounge from the ice shed.
Imagining yourself watching a game on Sheet C?
A couple views back towards the warm room from the ice.
Back of the building framed. Opening for the garage style door.
Almost ready to attach some exterior walls.
In other news we've started rolling out information on club membership and plan to start accepting league registrations in the next few weeks. Stay tuned!