A good view of the layering in the walls. Next to the ice you have the layer of insulation, covered with a plastic moisture barrier, and the metal siding.
Insulation from the inside.
Progress after one day of wall work.
As they worked their way up, the warm room back door was installed. There are four doors into the building, two in the front, two in the back.
Far wall complete and starting to wrap around the warm room by Thursday
By the end of the week, the wall facing the road was complete.
And they started closing in the rest of the warm room.
This week we should see the rest of the exterior walls go up and hopefully some good progress on the roof.
Great Progress
ReplyDelete